Project: South Mead Hospital , Bristol, Avon
Value: >£110K
Duration: 130 days
Requirement:
Three important criteria had to be achieved – we had to prevent crows and other birds from picking up the ballast, the system had to be anchored without penetrating the roof water proofing and the system had to be discrete.
Solution:
Eco Environmental Services supplied CSCS carded 2-man team led by SSSTS team leader who installed our bespoke Ballast Netting kits to the affected area – these nets can be installed above head height or where a more discreet installation is required, directly on to the pebbles.
Access Strategy:
Internal access to affected areas
Comments:
Laborious and often time-consuming work that we completed on time and within budget
Further Ballast information can be found by visiting reduce-impact-residual-risk-installing-ballast-netting